Five Spires Academy

Project Summary

Preparation for construction and refurbishment of secondary school

Hospital.png

Education

Schedule of Work

Customer

New drainage
New foundations
Structural slab
Hard & soft landscaping

Seddon

Project Stats

Blank.png
Blank.png
Blank.png
Approx. Value

£230,000

30 Weeks

Services

Groundworks

Duration
Blank.png

Lichfield

Location
Blank.png

Steve Hughes

Site Manager
Jack Kennedy

Project Gallery