top of page
Benson Community School
Services
Groundworks
£200,000
Approx. Value
18 Weeks
Duration
Birmingham
Location
February 2019
Completion Date
Project Summary
Schedule of Work
Groundworks to enable construction of new extension.
Installed foundations: Piled Footings
Installed Ground Ring Beams
Beam & Block Floors
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.
bottom of page