M&E Strip Out
54,000
sq. ft
4 Weeks
Duration
Derby
Location
May 2015
Completion Date
Project Summary
Schedule of Work
Demolition and strip out of two major University lecture theatres
Strip out lecture theatre seating
Demolish staging and seat tiering
Remove floor finishes and suspended ceiling
Remove decorative wall finishes
Remove HVAC system, ducting & pipework, radiators
Remove doors, frames, floor-fixed balustrade and handrails