top of page
The Fort Retail Park
Services
Soft Strip Out
Internal Demolition
28,000
sq. ft
3 Weeks
Duration
Birmingham
Location
Gabe Pettitt
Snr. Site Manager
Project Summary
Schedule of Work
Strip out of three adjacent retail units at major retail park
Demolish dividing walls between units
Strip out offices and staff room
Strip out stock rooms and remove racking
Remove ceiling systems and floor coverings
Demolish changing areas
Remove and recycle all debris & waste materials
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.
bottom of page