Harding Law Building

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

8,000

sq. ft

4 Weeks

Duration

Birmingham

Location

Jack Kennedy

Site Manager

Project Summary

Schedule of Work

Strip out & internal demolition in historical University buildings

Remove floor finishes & wall panelling & finishes
Demolish non-load bearing walls & remove partitions
Removed HVAC system, ducting & pipework, radiators & associated plant
Strip out WC's & sanitary ware
Strip out electrical & data services equipment & cabling