SCC Data Centre
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Groundworks
41,000
sq. ft
20 Weeks
Duration
Birmingham
Location
John Treacy
Site Manager
Project Summary
Schedule of Work
Combined strip out and groundworks project at large data centre & offices
Strip Out:
Strip out floor finishes, raised floors & suspended ceilings
Remove HVAC system, radiators, sanitaryware
Remove electrical & data services equipment & cabling
Remove & disposed of wall finishes inc. tiles
Demolish covered walkway, curtain walling & block walls
Remove fixtures & fittings inc. windows, doors, panels, frames, glazing
Groundworks:
Excavation & filling with earthwork supports
Preparations for installation of storm drainage
Landscaping; clearance of vegetation & excavation
Installation of fencing
Concrete slab foundations
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.