top of page

Cineworld

Services

Soft Strip Out
Internal Demolition

53,000

sq. ft

2 Weeks

Duration

Wolverhampton

Location

Jack Kennedy

Site Manager

Project Summary

Schedule of Work

Strip out of multiple theatres and foyer at multiplex cinema

Strip out foyer including ticket counters & concession store
Remove theatre seating
Strip out WC's and sanitary ware
Remove floor finishes & wall finishes
Strip out suspended ceilings and grid
Demolish partition walls and glazed curtain walling & doors
Remove spiral staircases
Remove and recycle all debris & waste materials

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page