Baskerville School

Services

Groundworks

£200,000

Approx. Value

8 Weeks

Duration

Harborne

Location

Callum Atkins

Site Manager

Project Summary

Schedule of Work

Preparation for temporary classrooms

Cutting-in of new access road (suitable for fire tender).
Installations of new pad foundations for new temporary school block.
Installation of new retaining wall along access road (approx. 20m).
Bollard lighting.
Water booster base, supply of water for temporary cabins.
Power, foul & storm services to new classrooms.
All arisings kept on site.
Forming new bund.