top of page

Baskerville School

Services

Groundworks

£200,000

Approx. Value

8 Weeks

Duration

Harborne

Location

Callum Atkins

Site Manager

Project Summary

Preparation for temporary classrooms

Schedule of Work

Cutting-in of new access road (suitable for fire tender).
Installations of new pad foundations for new temporary school block.
Installation of new retaining wall along access road (approx. 20m).
Bollard lighting.
Water booster base, supply of water for temporary cabins.
Power, foul & storm services to new classrooms.
All arisings kept on site.
Forming new bund.

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page