Soft Strip Out
M&E Strip Out
5,000
sq. ft
2 Weeks
Duration
Coventry
Location
Roman Gujda
Site Manager
Project Summary
Schedule of Work
Soft strip out of University administration office; 7th floor of city centre building
Strip out floor finishes, raised floors & suspended ceilings
Demolish non-load bearing walls & remove partitions
Dismantle & remove HVAC systems & ducting, electrical services & data services
Remove and recycle all debris & waste materials