top of page

Rugby 661

Services

Principal Contractor
Strip Out
M&E Strip Out

661,000

sq. ft

32 Weeks

Duration

Rugby

Location

Gabe Pettitt

Snr. Site Manager

Project Summary

Schedule of Work

Principal contractor for the strip out of one of Europe's largest automated warehouses.

Remove 330,000 sq. ft of racking, 12m in height
Remove high level conveyors & dock leveller gantry
Strip out offices and M&E including plant rooms
Disassemble two large steel mezzanines for re-use (6,728m2 & 3,092m2)
Remove two smoke walls between chambers & wind posts
Remove rooftop AHU's & ducting

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page