Project Summary

Schedule of Work

Strip out of this prestigious theatre's lobby and bar area

Dismantle & remove glazed entrance lobby & box office counter
Strip out kitchen area plus section of wall & risers, plus waiter station
Strip out bar area including associated services and counter top
Remove circular seating, ceilings, floor finishes and partitions
Strip out WC sanitaryware and cubicles
Cut back & remove cills & steps, form single door openings