Radcliffe Conference Centre
Services
Soft Strip Out
Internal Demolition
£40,000
sq. ft
5 Weeks
Duration
Coventry
Location
Lee Coates
Contracts Manager
Project Summary
Schedule of Work
Strip out & internal demolition of 75 hotel rooms and reception area at University conference centre ready for major refurbishment
Remove furniture, fixtures & fittings
Strip out floor finishes & suspended ceilings
Disconnect & Strip out WC's & sanitaryware, remove wall finishes
Strip out reception area desk, partition walls and glazing
Remove and recycle all debris & waste materials