top of page
Umberslade_Logo_Horizontal_PMS_WHT (reg)

Radcliffe Conference Centre

Services

Soft Strip Out
Internal Demolition

£40,000

sq. ft

5 Weeks

Duration

Coventry

Location

Lee Coates

Contracts Manager

Project Summary

Schedule of Work

Strip out & internal demolition of 75 hotel rooms and reception area at University conference centre ready for major refurbishment

Remove furniture, fixtures & fittings
Strip out floor finishes & suspended ceilings
Disconnect & Strip out WC's & sanitaryware, remove wall finishes
Strip out reception area desk, partition walls and glazing
Remove and recycle all debris & waste materials

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page