Addenbrooke House

Strip out & Demolition

Soft Strip Out
Internal Demolition

36,000

sq. ft

12 Weeks

Duration

Telford

Location

Jack Kennedy

Site Manager

Project Summary

Refurbish, to Warwick Uni Admin office and training rooms

Schedule of Work

Full strip out to shell (excluding RAF) of all office floor plates and WC’s from Ground floor to fourth floor. Removal of roof coverings and external curtain wall façade. 