Former Cov Press Factory
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Groundworks
280,000
sq. ft
12 Weeks
Duration
Coventry
Location
Gabe Pettitt
Snr. Site Manager
Project Summary
Schedule of Work
Internal demolition, strip out & groundworks at major manufacturing facility
Demolish internal warehouse walls and remove ceiling linings
Demolish pre-fabricated structures
Strip out damaged cladding panels
Dismantle mezzanine floors
Remove loading doors, access ladders and high-level plant gantries.
Remove roof-mounted process extraction systems, air scrubbing systems, pipework and other HVAC
Remove & renew damaged / displaced kerbs, edgings, and paving
Strip out canteen, kitchen, stores and WCs
Concrete cutting/breaking out, localised removal & reinstatement of concrete yard surfaces
Infill of existing machine press pits through both mass fill and reinforced concrete slabs cast onto a multi-deck system
Remove and recycle all debris & waste materials
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.