Project Summary

Schedule of Work

Internal demolition, strip out & groundworks at major manufacturing facility

Demolish internal warehouse walls and remove ceiling linings
Demolish pre-fabricated structures
Strip out damaged cladding panels
Dismantle mezzanine floors
Remove loading doors, access ladders and high-level plant gantries.
Remove roof-mounted process extraction systems, air scrubbing systems, pipework and other HVAC
Remove & renew damaged / displaced kerbs, edgings, and paving
Strip out canteen, kitchen, stores and WCs
Concrete cutting/breaking out, localised removal & reinstatement of concrete yard surfaces
Infill of existing machine press pits through both mass fill and reinforced concrete slabs cast onto a multi-deck system
Remove and recycle all debris & waste materials

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page