top of page
Purley Way
Services
Demolition
21,500
sq. ft
3 Weeks
Duration
Croydon
Location
February 2021
Completion Date
Project Summary
Schedule of Work
Removal of exterior canopy, glazed curtain walling and cladding from large retail unit
Dismantling & removal of glazed curtain walling
Removal of sections of steel structure
Removal of cladding & roof panelling
Demolition of block walls
Removal of roller shutters
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.