top of page
Umberslade Strip out Logo Horizontal

Clothier Road, Bristol

Office

Soft Strip Out
Demolition

14,000

sq. ft

5 Weeks

Duration

Bristol

Location

Jaroslav Kirvej

Site Manager

Project Summary

Strip-out, to allow new tenants office space

Schedule of Work

Full strip out to floor plates (4 floors from basement to 2nd) including Partitions, glazing and block walls. Remove WCs and M & E installations to all floors including external plant