Osborne Primary School

Services

Soft Strip Out
Internal Demolition
M&E Strip Out
Groundworks

16,000

sq. ft

52 Weeks (Phased)

Duration

Erdington

Location

Gabe Pettitt

Snr. Site Manager

Project Summary

Schedule of Work

Our strip out & groundworks teams work together to prepare a school of historical interest for a major refurbishment

Strip Out
Removal of lathe & plaster ceilings & stud partition walls
Removal of doors & frames, windows & window boards, parquet flooring, vinyl flooring & carpets, skirting boards, dado rails, picture rails, curtains, blinds & pelmets
Removal of kitchen, sanitary ware and M&E installations

Groundworks
Drainage work, installation of attenuation tank
Internal floor slab replacement in two buildings
Underpinning of main building
Build in-situ concrete stairs to basement
Concrete raft foundations
Formation of structural openings

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page