Jamies Restaurant

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

6,700

sq. ft

6 Weeks

Duration

Birmingham

Location

December 2020

Completion Date

Project Summary

Schedule of Work

Strip out of Mechanical & Electrical services and mezzanine structure at large city-centre restaurant

Dismantle & remove Mezzanine structure
Remove HVAC plant & ducting & roof level plant & electrical services
Strip out WC's and sanitary ware
Removed shop fit panelling, partition walls & glazing
Created new openings
Remove and recycle all debris & waste materials