Dosthill Primary Academy

Services

Groundworks

£350,000

Approx. Value

25 Weeks

Duration

Tamworth

Location

Tom Hewitt

Site Manager

Project Summary

Schedule of Work

Drainage, concreting work & hard landscaping at Primary School in Tamworth.

Drainage works including installation of a Foul Pumping Station (depth 4.5m) and a Storm Pumping Station (3.1m)
Tarmac footpath to new build and regrade/topsoil
Extend playground area
Topsoiling to existing school field
Construct concrete upstand wall to perimeter
Removal of timber haul road