sq. ft60,000
Duration2.5 Weeks
LocationPeterborough
Site ManagerDean Marshall

Project Summary

Strip out of offices & demolition of dividing wall within warehouse

Schedule of Work

Strip out of floor finishes, suspended ceilings, partition walls
Remove HVAC plant & ducting & roof level plant & electrical services
Demolition of two story dividing wall (including above roof-top)
Demolition of beam & block flooring and structural steel frame
Remove and recycle all debris & waste materials