Umberslade

EducationSoft Strip Out Internal Demolition M&E Strip Out
sq. ft2,500
Duration1 Week
LocationBirmingham
Site ManagerJohn Treacy

Project Summary

Soft strip out of former NHS offices prior to Category ‘A’ refurbishment for Aston University

Schedule of Work

Remove floor surfaces
Strip out partition walls
Remove electrical & data services equipment & cabling
Remove of kitchen & 3 roller-racking systems