Umberslade

EducationSoft Strip Out Internal Demolition M&E Strip Out Groundworks
sq. ft16,000
Duration52 Weeks (Phased)
LocationErdington
Snr. Site ManagerGabe Pettitt

Project Summary

Our strip out & groundworks teams work together to prepare a school of historical interest for a major refurbishment

Schedule of Work

Strip Out
Removal of lathe & plaster ceilings & stud partition walls
Removal of doors & frames, windows & window boards, parquet flooring, vinyl flooring & carpets, skirting boards, dado rails, picture rails, curtains, blinds & pelmets
Removal of kitchen, sanitary ware and M&E installations

Groundworks
Drainage work, installation of attenuation tank
Internal floor slab replacement in two buildings
Underpinning of main building
Build in-situ concrete stairs to basement
Concrete raft foundations
Formation of structural openings

Time-lapse video: Concrete pour

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

Get a Quote

Have a programme like this?