Windrush Court
Project Summary
Full office strip out, including furniture M&E, data services and security systems

Commercial
Schedule of Work
Remove previous tenant's furniture, fixtures & fittings
Strip out floor finishes, raised floors & suspended ceilings
Remove HVAC system, ducting & pipework, radiators & associated roof level plant
Strip out WC's & sanitaryware
Remove electrical & data services equipment & cabling
Strip out & remove intruder alarm, CCTV system & all associated cabling
Project Gallery
Project Stats



sq. ft
12,800
2 Weeks
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Duration

Oxford
Location

John Treacy
Site Manager