Project Summary
Dismantling of exhibits and strip out of gift shop at major visitor attraction

Hospitality & Leisure
Schedule of Work
Dismantle & remove exhibits
Remove false trees, street lights & other props
Strip out retail shelves & remove store counter
Remove entrance turnstile units
Remove and recycle all debris & waste materials
Project Gallery
Project Stats



Approx. Value
<£10,000
3 Days
Services
Soft Strip Out
Internal Demolition
Duration

Birmingham
Location

Lee Coates
Contracts Manager