Temple Street

Project Summary

Acting as principal contractor to strip out 5 office floors for a leading property -management company

Hospital.png

Commercial

Schedule of Work

Demolish partitions, remove glazed screens & doors
Remove floor finishes, skirtings & suspended ceilings
Remove wall panelling systems & plasterboard column casings
Remove WC's and wall tiles
Dismantle & remove HVAC systems & ducting, electrical services & data services

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

60,000

11 Weeks

Services

Principal Contractor
Soft Strip Out
Internal Demolition
M&E Strip Out

Duration
Blank.png

Birmingham

Location
Blank.png

Jack Kennedy

Site Manager
Jack Kennedy