Acting as principal contractor to strip out 5 office floors for a leading property -management company

Commercial
Schedule of Work
Demolish partitions, remove glazed screens & doors
Remove floor finishes, skirtings & suspended ceilings
Remove wall panelling systems & plasterboard column casings
Remove WC's and wall tiles
Dismantle & remove HVAC systems & ducting, electrical services & data services
Project Gallery
Project Stats



sq. ft
60,000
11 Weeks
Services
Principal Contractor
Soft Strip Out
Internal Demolition
M&E Strip Out
Duration

Birmingham
Location

Jack Kennedy
Site Manager