Purley Way
Project Summary
Removal of exterior canopy, glazed curtain walling and cladding from large retail unit

Retail
Schedule of Work
Dismantling & removal of glazed curtain walling
Removal of sections of steel structure
Removal of cladding & roof panelling
Demolition of block walls
Removal of roller shutters
Project Gallery
Project Stats



sq. ft
21,500
3 Weeks
Services
Demolition
Duration

Croydon
Location