Purley Way

Project Summary

Removal of exterior canopy, glazed curtain walling and cladding from large retail unit

Hospital.png

Retail

Schedule of Work

Dismantling & removal of glazed curtain walling
Removal of sections of steel structure
Removal of cladding & roof panelling
Demolition of block walls
Removal of roller shutters

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

21,500

3 Weeks

Services

Demolition

Duration
Blank.png

Croydon

Location
Blank.png

Ken Taylor

Site Manager
Jack Kennedy