Osborne Primary School
Project Summary
Our strip out & groundworks teams work together to prepare a school of historical interest for a major refurbishment

Education
Schedule of Work
Strip Out
Removal of lathe & plaster ceilings & stud partition walls
Removal of doors & frames, windows & window boards, parquet flooring, vinyl flooring & carpets, skirting boards, dado rails, picture rails, curtains, blinds & pelmets
Removal of kitchen, sanitary ware and M&E installations
Groundworks
Drainage work, installation of attenuation tank
Internal floor slab replacement in two buildings
Underpinning of main building
Build in-situ concrete stairs to basement
Concrete raft foundations
Formation of structural openings
Project Gallery
Project Stats



sq. ft
16,000
52 Weeks (Phased)
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Groundworks
Duration

Erdington
Location

Gabe Pettitt
Snr. Site Manager