
Orton 130
Project Summary
Strip out of offices & demolition of dividing wall within warehouse

Industrial
Schedule of Work
Customer
Strip out of floor finishes, suspended ceilings, partition walls
Remove HVAC plant & ducting & roof level plant & electrical services
Demolition of two story dividing wall (including above roof-top)
Demolition of beam & block flooring and structural steel frame
Remove and recycle all debris & waste materials
DP Designs
Project Stats



sq. ft
60,000
2.5 Weeks
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Duration

Peterborough
Location

Dean Marshall
Site Manager
