Jamies Restaurant
Project Summary
Strip out of Mechanical & Electrical services and mezzanine structure at large city-centre restaurant

Hospitality & Leisure
Schedule of Work
Dismantle & remove Mezzanine structure
Remove HVAC plant & ducting & roof level plant & electrical services
Strip out WC's and sanitary ware
Removed shop fit panelling, partition walls & glazing
Created new openings
Remove and recycle all debris & waste materials
Project Gallery
Project Stats



sq. ft
6,700
6 Weeks
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Duration

Birmingham
Location

Ken Taylor
Site Manager