Dismantle & remove Mezzanine structure
Remove HVAC plant & ducting & roof level plant & electrical services
Strip out WC's and sanitary ware
Removed shop fit panelling, partition walls & glazing
Created new openings
Remove and recycle all debris & waste materials

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

6,700

6 Weeks

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

Duration
Blank.png

Birmingham

Location
Blank.png

Ken Taylor

Site Manager
Jack Kennedy