Hall of Residence, UoB
Project Summary
Strip out & internal demolition of student accommodation

Education
Schedule of Work
Soft strip furniture, fixtures & fittings from bedrooms, kitchens & common rooms
Strip out of floor finishes, fixtures & skirtings
Internal demolition of partition walls, making good disturbed floors
Strip out of shower areas, bathrooms & WCs inc. pipework
Strip out M&E from laundry, redundant electrical/ventilation inc. roof plant
Remove racking & shelving from storage areas
Removal & recycling of waste material
Project Gallery
Project Stats



sq. ft
90,000
14 Weeks
Services
Soft Strip Out
M&E Strip Out
Internal Demolition
Duration

Birmingham
Location

Jack Kennedy
Site Manager