Former GAP Warehouse
Project Summary
Principal contractor for the strip out of one of Europe's largest automated warehouses.

Commercial
Schedule of Work
Remove 330,000 sq. ft of racking, 12m in height
Remove high level conveyors & dock leveller gantry
Strip out offices and M&E including plant rooms
Disassemble two large steel mezzanines for re-use (6,728m2 & 3,092m2)
Remove two smoke walls between chambers & wind posts
Remove rooftop AHU's & ducting
Project Gallery
Project Stats



sq. ft
661,000
32 Weeks
Services
Strip Out, M&E Strip Out
Duration

Rugby
Location

Gabe Pettitt
Snr. Site Manager