Project Summary

Removal of electrical services at large industrial facility

Hospital.png

Industrial

Schedule of Work

Remove electrical cables, distribution boards and power supplies
Remove electrical trunking system & floodlight fittings & wiring
Remove and recycle all debris & waste materials

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

89,0000

3 Weeks

Services

M&E Strip Out

Duration
Blank.png

Wolverhampton

Location
Blank.png

Patrik Kirvej

Site Manager