Dosthill Primary Academy

Project Summary

Drainage, concreting work & hard landscaping at Primary School in Tamworth.

Hospital.png

Education

Schedule of Work

Drainage works including installation of a Foul Pumping Station (depth 4.5m) and a Storm Pumping Station (3.1m)
Tarmac footpath to new build and regrade/topsoil
Extend playground area
Topsoiling to existing school field
Construct concrete upstand wall to perimeter
Removal of timber haul road

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
Approx. Value

<£350,000

25 Weeks

Services

Groundworks

Duration
Blank.png

Tamworth

Location
Blank.png

Dave Reid

Site Manager
Jack Kennedy