Air Space

Project Summary

Strip out of former trampoline park, including removal of large concrete plank mezzanine

Hospital.png

Hospitality & Leisure

Schedule of Work

Strip out trampolines, soft play areas, gymnastics equipment & safety netting & boarding
Strip out high level access gantry, inc. fixtures & fittings
Remove glass balustrades & handrails
Strip out floor finishes back to floor slab
Dismantle & demolish first floor mezzanine inc. pedestals & support structure
Strip out ceilings, kitchens, WC's, partitioning
Strip out M&E services inc plant, ducting & HVAC equipment.
Remove elevator (public lift)

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

4,900

12 Weeks

Services

Soft Strip Out
Internal Demolition

Duration
Blank.png

Wolverhampton

Location
Blank.png

Gabe Pettitt

Snr. Site Manager
Jack Kennedy