Air Space
Project Summary
Strip out of former trampoline park, including removal of large concrete plank mezzanine

Hospitality & Leisure
Schedule of Work
Strip out trampolines, soft play areas, gymnastics equipment & safety netting & boarding
Strip out high level access gantry, inc. fixtures & fittings
Remove glass balustrades & handrails
Strip out floor finishes back to floor slab
Dismantle & demolish first floor mezzanine inc. pedestals & support structure
Strip out ceilings, kitchens, WC's, partitioning
Strip out M&E services inc plant, ducting & HVAC equipment.
Remove elevator (public lift)
Project Gallery
Project Stats



sq. ft
4,900
12 Weeks
Services
Soft Strip Out
Internal Demolition
Duration

Wolverhampton
Location

Gabe Pettitt
Snr. Site Manager