Dirft

Industrial

Soft Strip Out
Demolition

325,000

sq. ft

12 weeks

Duration

Daventry

Location

Gabe Pettitt

Project Summary

Full strip out of warehouse and office space and external works

Schedule of Work

Full strip out of pallets racking system and 2 tier mezzanine to large warehouse. Removal of tenant installed M&E to the warehouse.
Full strip to office space, including floor coverings, ceilings, partitions and full M&E removal Demolition of single story of tenant installed house and external steel staircase.