IndustrialPrincipal contractor Soft strip out M&E strip out Internal demolition
sq. ft661,000
Duration32 Weeks
LocationRugby
Snr. Site ManagerGabe Pettitt
Project Summary
Principal contractor for the strip out of one of Europe’s largest automated warehouses.
Schedule of Work
Remove 330,000 sq. ft of racking, 12m in height
Remove high level conveyors & dock leveller gantry
Strip out offices and M&E including plant rooms
Disassemble two large steel mezzanines for re-use (6,728m2 & 3,092m2)
Remove two smoke walls between chambers & wind posts
Remove rooftop AHU’s & ducting
Time-lapse Video
Concrete pour on Ground Ring Beams
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.
