OfficeOffice Soft Strip Out Internal Demolition M&E Strip Out
sq. ft75,000
Duration3 Weeks
LocationWelwyn Garden City
Contracts ManagerJack Morton
Project Summary
Office strip out of Ocado’s head office, including M&E strip out.
Schedule of Work
Remove vinyl plank & tile floor coverings
Strip out suspended ceilings and grid
Remove fixtures & fittings
Strip out tea points & kitchen
M&E strip out of data & electrical services, AC cassettes & pipework
Demolish & remove concrete staircase
Strip out plasterboard & glazed partitions and jumbo stud wall