Project Summary

Strip out of Robins & Day Citroen/Peugeot dealership, including showroom, sales offices and staff areas.

Schedule of Work

Strip out counter units and fixtures & fittings
Demolish partition walls & glazed partitions
Remove carpets, barrier matting & vinyl floor surfaces
Remove ceramic & timber skirting
Strip out suspended ceiling tiles
Strip out canteen & WCs
Remove external signage