Project Summary
Foundation work and installation & alteration of services for new and existing buildings.
Schedule of Work
Reduce level dig in internal courtyard, arisings tip off site
Cast new foundation with steel frame
Internal floor slabs for ground floor & first floor
Bases for external AHU’s, ground and roof level
Alterations to external drainage
Drainage work for new buildings