AutomotiveSoft Strip Out
sq. ft2,000
Duration1 Week
LocationReading
Site ManagerDean Stanley

Project Summary

Strip out of car showroom and sales offices, plus WCs and canteen areas

Schedule of Work

Remove plasterboard & glazed partitions
Strip out fixtures & fittings, WCs & canteen
Strip out carpets, vinyl floor surfaces & ceramic floor tiles
Strip out suspended ceiling; tiles & grid
Remove radiators & pipework
Remove signage & noticeboards