Umberslade

Hospitality & LeisureSoft Strip Out Internal Demolition M&E Strip Out
sq. ft6,700
Duration6 Weeks
LocationBirmingham
Completion DateDecember 2020

Project Summary

Strip out of Mechanical & Electrical services and mezzanine structure at large city-centre restaurant

Schedule of Work

Dismantle & remove Mezzanine structure
Remove HVAC plant & ducting & roof level plant & electrical services
Strip out WC’s and sanitary ware
Removed shop fit panelling, partition walls & glazing
Created new openings
Remove and recycle all debris & waste materials

Minimum fuss. Maximum service.