sq. ft280,000
Duration12 Weeks
LocationCoventry
Snr. Site ManagerGabe Pettitt

Project Summary

Internal demolition, strip out & groundworks at major manufacturing facility

Schedule of Work

Demolish internal warehouse walls and remove ceiling linings

Demolish pre-fabricated structures

Strip out damaged cladding panels

Dismantle mezzanine floors

Remove loading doors, access ladders and high-level plant gantries.

Remove roof-mounted process extraction systems, air scrubbing systems, pipework and other HVAC

Remove & renew damaged / displaced kerbs, edgings, and paving

Strip out canteen, kitchen, stores and WCs

Concrete cutting/breaking out, localised removal & reinstatement of concrete yard surfaces

Infill of existing machine press pits through both mass fill and reinforced concrete slabs cast onto a multi-deck system

Remove and recycle all debris & waste materials

Time Lapse Video: Concrete Pour

Infill of existing machine press pits through both mass fill and reinforced concrete slabs cast onto a multi-deck system

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

Get a Quote

Have a programme like this?