OfficeSoft Strip Out Demolition
sq. ft14,000
5 WeeksDuration
LocationBristol
Site ManagerJaroslav Kirvej

Project Summary

 Strip-out, to allow new tenants office space

Schedule of Work

Full strip out to floor plates (4 floors from basement to 2nd) including Partitions, glazing and block walls. Remove WCs and M & E installations to all floors including external plant