Project Summary
Soft strip out of large office in central Milton Keynes
Schedule of Work
Remove ceiling grid and tiles
Remove door sets & frames, window blinds, fixtures & fittings
Strip out stud partitioning & glazed partitions
Demolish & remove blockwork walls
Strip out kitchenettes, including water heaters and pipework
Strip out WC’s sanitaryware, cubicles & wall panelling
Strip out A/C, heating and electrical equipment, radiators, ductwork and pipework