CASE STUDY : COLD STORAGE FACILITIES DECONSTRUCTION
Project
Deconstruction of cold storage facilities and clearance of workshop areas
Location
University of Warwick Campus, Wellesbourne
Services
Strip out & Demolition
Duration
2 weeks
Main Contractor
Chiel Construction
Value of Project
£20,000
Work Carried Out
-
Removal of cold storage rooms and associated plant
-
Demolition of raised concrete slab
-
Removal of vinyl floor covering