CASE STUDY : CHANGE OF USE - OFFICE TO RESIDENTIAL
Project
Strip out & internal demolition (back to shell) for office-to-residential conversion
Location
Thames Valley Business Park, Bracknell
Services
Strip out / Internal demolition
Duration
12 weeks
Main Contractor
Colmore Tang

Value of Project
£250k
Umberslade Site Manager
Jack Morton
COVID-19 Precautions
-
This project was completed prior to the onset of the COVID-19 pandemic
Work Carried Out
-
Glazing removal in Atrium, ceiling finishes & balcony bulkheads
-
Strip out of reception area & coffee shop
-
Strip out WC’s, cubicles, sanitary ware, ceilings, floor tiles & partitions (back to shell)
-
Strip out of office (back to shell), including floor finishes, ceiling finishes, stud & glazed partitions, plasterboard wall linings & folding walls
-
Remove raised access floor system and all M&E
-
Strip out plant rooms & roof plant
-
Provide protection to stairs, hand rails and tiled flooring