1/13

CASE STUDY : CITY CENTRE STRIP OUT

Project

Strip out of offices and removal of major plant

Location

Great Charles Street, Birmingham

Services

Strip out

Duration

2 weeks​

Main Contractor

Avondale Interiors

Value of Project

£100,000

Work Carried Out
  • Partitions, carpet  & ceiling tile removal from multiple floors

  • Removed air conditioning plant (two interior plant rooms & roof top)

  • A gantry was custom-built to faciltate plant removal from the roof top

PUNCTUAL

Stephen Pallett, Contracts Manager

Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.

 

  • LinkedIn Social Icon
  • Twitter Social Icon
  • Facebook Social Icon
  • YouTube Social  Icon

© 2020 Umberslade Business Services Ltd.

Umberslade White 300dpi_capabilities_log