CASE STUDY : SMALL BUILDING DEMOLITION

Project

Strip out and demolition of a pre-war Scout Hut

Location

Berkswell Village, Nr. Coventry

Services

Strip Out & Demolition

Duration

8 Days

Main Contractor

Stanford Construction

Value of Project

£8,000

Work Carried Out
  • Strip out of all recyclable materials

  • Demolish structure

  • Clear area ready for construction of new building

PUNCTUAL

Stephen Pallett, Contracts Manager

Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.

 