Victoria Community School
Project Summary
Groundworks project in a community special school. Includes re-location of a large stone circle and time-capsule.

Education
Schedule of Work
Project in a community special school requiring extra consideration
Re-location of stone circle & time-capsules (see time-lapse)
Drainage work, installation of attenuation tank
Install pumping station
Installation of Grasscrete eco-friendly car park
Project Gallery
Project Stats



Approx. Value
£950,000
52 Weeks
Services
Groundworks
Duration

Birmingham
Location

Steve Hughes
Contracts Manager