The Fort Retail Park
Project Summary
Strip out of three adjacent retail units at major retail park

Retail
Schedule of Work
Demolish dividing walls between units
Strip out offices and staff room
Strip out stock rooms and remove racking
Remove ceiling systems and floor coverings
Demolish changing areas
Remove and recycle all debris & waste materials
Project Gallery
Project Stats



sq. ft
28,000
3 Weeks
Services
Soft Strip Out
Internal Demolition
Duration

Birmingham
Location

Gabe Pettitt
Snr. Site Manager