The Fort Retail Park

Project Summary

Strip out of three adjacent retail units at major retail park

Retail

Schedule of Work

Customer

Demolish dividing walls between units
Strip out offices and staff room
Strip out stock rooms and remove racking
Remove ceiling systems and floor coverings
Demolish changing areas
Remove and recycle all debris & waste materials

Lawfield Contracts

Project Stats

Project Value

£70,000

3 Weeks

Services

Soft Strip Out
Internal Demolition

Duration

Birmingham

Location

Gabe Pettitt

Site Manager

Project Gallery

PUNCTUAL

Stephen Pallett, Contracts Manager

“Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.”